ARSD 74:05:08:13.02
Any applicant requesting assistance for a wastewater treatment works or storm water project must prepare a facilities plan. A facilities plan is not required from an applicant requesting funding for other types of projects. The facilities plan shall at minimum provide the information contained in subdivision 74:05:08:01(6). The applicant shall be notified of any deficiencies in the draft facilities plan submitted with the application. A completed facilities plan must be received by the department to initiate the environmental review process. The facilities plan is not considered complete until the following items are received:
Source: 33 SDR 106, effective December 26, 2006; 36 SDR 208, effective June 28, 2010; 40 SDR 14, effective July 29, 2013 ; 49 SDR 100, effective May 22, 2023 .
General Authority: SDCL 46A-1-60.3 .
Law Implemented: SDCL 46A-1-60.1 to 46A-1-60.3 , inclusive .
Prior versions effective: 2013-07-29.