ARSD 74:02:08:07
The hydraulic capacity of a dam must, by category and size, be such that the following minimum spillway design floods can be passed through the spillways without overtopping the structure:
CATEGORY
SIZE
SPILLWAY DESIGN FLOOD
3
Small
50-year frequency unless dam
qualifies for § 74:02:08:07.01
exception
Intermediate
100-year frequency
Large
0.5 PMF
2
Small
100-year frequency
Intermediate
0.5 PMF, unless dam qualifies
for § 74:02:08:07.02 exception
Large
PMF
1
Small
0.5 PMF
Intermediate
0.5 PMF
Large
PMF
A spillway system for a dam must meet the requirements in this section unless the owner can provide information and justification to show the chief engineer that the proposed design flow can be stored, passed through, or passed over the dam without failure of the dam or if a variance is granted pursuant to SDCL 46-7-5.3.
Source: 13 SDR 49, effective October 27, 1986; 13 SDR 129, 13 SDR 141, effective July 1, 1987; 13 SDR 197, effective July 2, 1987; 14 SDR 67, effective November 8, 1987.
General Authority: SDCL 46-2-5 , 46-7-3.
Law Implemented: SDCL 46-5-8 , 46-5-30 , 46-7-3 , 46-7-5 , 46-7-5.3.