ARSD 74:02:04:60
Requirements for installation of pumps are as follows:
(3) Wells with a pump capacity of more than 18 gallons per minute and a casing size 8 inches or larger must have at least a one-inch threaded hole and a plug at the top of the well that allows measurement of the water level.
If the driller does not install the pump, the pump installer is responsible for installation of the pump and final disinfection of the well after installation of the pump.
Source: SL 1975, ch 16, § 1; transferred from § 52:01:04:08, effective July 1, 1979; transferred from § 74:02:04:08, 12 SDR 50, effective September 29, 1985; 13 SDR 129, 13 SDR 141, effective July 1, 1987; 18 SDR 224, effective July 16, 1992.
General Authority: SDCL 46-2-5 , 46-6-6.1 , 46-6-20.
Law Implemented: SDCL 46-6-6.1 , 46-6-20.