ARSD 70:04:05:08.02
The criteria for considering permit application for power and communication lines are as follows:
(3) Attachments for electric power and communication lines must provide sufficient clearance for convenience and safety during maintenance and repair of bridge structure or other utility installations on the bridge.
Metallic conduit attached to structures that are cathodically protected must meet all of the requirements in this section and may not adversely affect the cathodic protection of the structure. Such an attachment must insulate the conduit from the soil and use anodes at each end for grounding. The specific method proposed to be used must be specified in the permit application and is subject to approval by the region engineer.
Source: 20 SDR 159, effective April 3, 1994.
General Authority: SDCL 31-26-22.
Law Implemented: SDCL 31-26-22.