ARSD 61:08:06:07
Any new boiler to be installed in the state of South Dakota shall be reported by the installer to the State Fire Marshal's Office except any boiler exempted by SDCL 34-29A-14. Any new boiler shall meet the following requirements:
(5) Each hot water supply boiler operating with a BTU input of two hundred thousand or more shall be equipped with temperature and pressure relief valves bearing appropriate American Gas Association ratings or with electric high limit actuated controls of the emersion type located at the highest practicable section of the hot water supply boiler. The electric controls may be accepted when wired in series with the combustion control and the boiler is equipped with the right size ASME relief valve.
Reference: ASME Boiler and Pressure Vessel Code, July 1, 2021, edition, sections I and IV. Copies may be obtained from the American Society of Mechanical Engineers, Two Park Avenue, New York, NY 10016. Section I, $508; section IV, $517.
Source: SL 1975, ch 16, § 1; 5 SDR 61, effective January 28, 1979; 8 SDR 87, 8 SDR 134, effective July 1, 1982; 12 SDR 151, 12 SDR 155, effective July 1, 1986; 30 SDR 48, effective October 16, 2003 ; 50 SDR 47, effective October 16, 2023 .
General Authority: SDCL 34-29A-16 .
Law Implemented: SDCL 34-29A-23 .
Prior versions effective: 2003-10-16.