ARSD 20:44:18:02
A w iring permit may be obtained for twenty dollars from the commission office.
A wiring permit is valid for three years from the date the permit is issued. An electrical installation that extends beyond three years from the date of issuance must have a new wiring permit posted and sent to the commission office before the expiration date. Failure to date the wiring permit at the start of the job constitutes a late wiring permit procedure and subjects the installer to a two-hundred-fifty-dollar administrative fee. Failure to renew the permit for an electrical installation that is not completed constitutes a late wiring permit procedure that subjects the installer to a two-hundred-fifty-dollar administrative fee.
Source: SL 1975, ch 16, § 1; 5 SDR 1, effective July 20, 1978; 12 SDR 92, effective January 1, 1986; 12 SDR 151, 12 SDR 155, effective July 1, 1986; 20 SDR 222, effective July 6, 1994; transferred from § 20:44:04:02, August 12, 1994; 28 SDR 178, effective July 1, 2002; 32 SDR 37, effective September 1, 2005; 37 SDR 236, effective June 29, 2011; 46 SDR 128, effective May 26, 2020 ; 51 SDR 140, effective July 1, 2025 .
General Authority: SDCL 36-16-12 , 36-16-30 .
Law Implemented: SDCL 36-16-27 , 36-16-28 , 36-16-30 .
Prior versions effective: 2020-05-26, 2011-06-29.