ARSD 20:10:36:59
Upon completion of the tier 4 interconnection facilities study and execution of an agreement between the parties detailing progress billing, final billing, payment schedules, and deposit, the public utility shall approve the application.
Source: 35 SDR 305, effective July 1, 2009.
General Authority: SDCL 49-34A-27 , 49-34A-93.
Law Implemented: SDCL 49-34A-27 , 49-34A-93.