ARSD 20:10:36:50
The public utility shall use the tier 4 interconnection review procedures for an application that does not qualify for tier 1, tier 2, or tier 3 review and for which the small generator facility has an electric nameplate capacity that is ten megawatts or less. The public utility may not impose additional requirements.
Source: 35 SDR 305, effective July 1, 2009.
General Authority: SDCL 49-34A-27 , 49-34A-93.
Law Implemented: SDCL 49-34A-27 , 49-34A-93.