The tier 2 interconnection process is complete when:
- (1) All tier 2 screening criteria are satisfied and any minor EDS modifications are implemented;
- (2) The small generator facility installation is approved by an electric code inspector with jurisdiction over the interconnection;
- (3) The witness test, if conducted by the public utility, is successful;
- (4) The parties execute a certificate of completion; and
- (5) An interconnecting agreement has been executed.
Source: 35 SDR 305, effective July 1, 2009.
General Authority: SDCL 49-34A-27 , 49-34A-93.
Law Implemented: SDCL 49-34A-27 , 49-34A-93.