ARSD 20:10:36:36
The public utility shall use the tier 2 review procedures for an application of a small generator facility that meets the following requirements:
(3) The proposed facility will use interconnection equipment that is either lab tested equipment or field tested equipment.
The public utility may not impose additional requirements not specifically authorized.
Source: 35 SDR 305, effective July 1, 2009.
General Authority: SDCL 49-34A-27 , 49-34A-93.
Law Implemented: SDCL 49-34A-27 , 49-34A-93.