The public utility shall use the tier 1 review procedures for a small generator facility application that meets the following requirements:
(4) The proposed point of interconnection is not to a transmission line.
A public utility may not impose additional requirements to a tier 1 interconnection application.
Source: 35 SDR 305, effective July 1, 2009.
General Authority: SDCL 49-34A-27 , 49-34A-93.
Law Implemented: SDCL 49-34A-27 , 49-34A-93.