ARSD 20:10:36:14
The public utility may propose to interconnect more than one small generator facility at a single point of interconnection in order to minimize costs, and may not unreasonably refuse a request to do so. However, an applicant or an interconnection customer may elect to pay the entire cost of separate interconnection facilities.
Source: 35 SDR 305, effective July 1, 2009.
General Authority: SDCL 49-34A-27 , 49-34A-93.