The applicant shall provide the following information describing the proposed gas or liquid transmission line:
- (1) A flow diagram showing daily design capacity of the proposed transmission facility;
- (2) Changes in flow in the transmission facilities connected to the proposed facility;
- (3) Technical specifications of the pipe proposed to be installed, including the certified maximum operating pressure, expressed in terms of pounds per square inch gauge (psig);
- (4) A description of each new compressor station and the specific operating characteristics of each station; and
- (5) A description of all storage facilities associated with the proposed facility.
Source: 7 SDR 41, effective November 3, 1980; 12 SDR 151, 12 SDR 155, effective July 1, 1986.
General Authority: SDCL 49-41B-35.
Law Implemented: SDCL 49-41B-11 , 49-41B-22.