If a transmission facility is proposed, the applicant shall provide the following information:
- (1) Configuration of the towers and poles, including material, overall height, and width;
- (2) Conductor configuration and size, length of span between structures, and number of circuits per pole or tower;
- (3) The proposed transmission site and major alternatives as depicted on overhead photographs and land use culture maps;
- (4) Reliability and safety;
- (5) Right-of-way or condemnation requirements;
- (6) Necessary clearing activities; and
- (7) If the transmission facility is placed underground, the depth of burial, distance between access points, conductor configuration and size, and number of circuits.
Source: 5 SDR 1, effective July 25, 1978; 12 SDR 151, 12 SDR 155, effective July 1, 1986; 32 SDR 109, effective December 26, 2005.
General Authority: SDCL 49-41B-35(2 )( 3).