Existing energy conversion facilities.
Effective May 30, 202147 SDR 125Source: 4 SDR 7, effective November 13, 1977; 12 SDR 151, 12 SDR 155, effective July 1, 1986 ; 47 SDR 125, effective May 30, 2021 . | General Authority: SDCL 49-41B-35 . | Law Implemented: SDCL 49-41B-3 (1), 49-41B-3 (4).
For existing energy conversion facilities, that are owned or operated by the utility to serve South Dakota load, the utility shall provide information as follows:
- (1) Location;
- (2) Type and nameplate capacity;
- (3) Net capacity and annual production in megawatt hours for each of the past two calendar years;
- (4) Water source and actual annual use and consumption in acre feet for each of the past two calendar years;
- (5) Fuel type and source and annual consumption of fuel for each of the past two calendar years;
- (6) Projected date of removal from service and the reason for removal; and
- (7) Decommissioning plans for any facility expected by the facility owner to be retired in the next ten years.
Source: 4 SDR 7, effective November 13, 1977; 12 SDR 151, 12 SDR 155, effective July 1, 1986 ; 47 SDR 125, effective May 30, 2021 .
General Authority: SDCL 49-41B-35 .
Law Implemented: SDCL 49-41B-3 (1), 49-41B-3 (4).