(1) If a manufacturer plans to produce at more than one (1) location, required plan approval may be obtained for all locations subject to submission of the following:
- (a) one (1) set of plan review application forms for each location; and
- (b) one electronic set of plans and specifications, plus one (1) additional set for each location specifying the location of manufacture; and
- (c) filing fees as designated in these regulations; and
- (d) one (1) electronic quality control manual for each location of manufacture.
- (2) If a manufacturer wishes to obtain approval for one (1) or more points of manufacture, a manufacture’s license, and at least one (1) manufacturer’s representative license must be issued for each location.
HISTORY: Added by State Register Volume 32, Issue No. 6, eff June 27, 2008. Amended by State Register Volume 37, Issue No. 5, eff May 24, 2013; State Register Volume 39, Issue No. 6, Doc. No. 4501, eff June 26, 2015; SCSR 48-5 Doc. No. 5248, eff May 24, 2024.