- (a) No later than September 1, 2024, the commission shall commence a process, which includes stakeholder engagement, to adopt a framework for an interconnection tariff for energy storage systems connected to the electric distribution system that recognizes the flexible operating characteristics of energy storage systems.
- (b) Following the public utilities commission’s adoption of a framework, which shall be completed no later than May 1, 2025, each electric distribution company as defined in § 39-1-2 that has greater than one hundred thousand (100,000) customers shall file a proposed energy storage system interconnection tariff for review and approval in a contested proceeding.
History of Section.
P.L. 2024, ch. 404, § 2, effective June 26, 2024; P.L. 2024, ch. 405, § 2, effective June 26, 2024.