(c) Expediting emergency work. Emergency work may be completed without installation of work zone traffic-control devices required by this subchapter, if one of the following conditions is met:
- (1) Review of the condition indicates that the emergency work can be completed in less time than it would take to install the temporary traffic-control devices, and the work or condition would not create a significant potential hazard.
- (2) Temporary traffic control has been set up and it is found that additional traffic-control devices are desirable, but that it would take longer to obtain and install additional traffic-control devices than it would to complete the work.