52 Pa. Code § 75.1
The following words and terms, when used in this chapter, have the following meanings unless the context clearly indicates otherwise:
Act—The Alternative Energy Portfolio Standards Act (73 P.S. § § 1648.1—1648.8), as amended by 66 Pa.C.S. § 2814 (relating to additional alternative energy sources).
Aggregator—A person or entity that maintains a contract with multiple individual alternative energy system owners to facilitate the sale of alternative energy credits on behalf of multiple alternative energy system owners.
Alternative energy credit—A tradable instrument that is used to establish, verify and monitor compliance with the act. A unit of credit must equal 1 megawatt hour of electricity from an alternative energy source. An alternative energy credit shall remain the property of the alternative energy system until the alternative energy credit is voluntarily transferred by the alternative energy system.
Alternative energy sources—The term includes the following existing and new sources for the production of electricity:
(v) Low-impact hydropower consisting of any technology that produces electric power and that harnesses the hydroelectric potential of moving water impoundments if one of the following applies:
(B) The incremental hydroelectric development:
(vii) Biomass energy, which means the generation of electricity utilizing the following:
(xii) Demand-side management consisting of the management of customer consumption of electricity or the demand for electricity through the implementation of:
(xiii) Distributed generation systems, which means the small-scale power generation of electricity and useful thermal energy from systems with a nameplate capacity not greater than 5 MW.
Alternative energy system—A facility or energy system that uses a form of alternative energy source to generate electricity and delivers the electricity it generates to the distribution system of an EDC or to the transmission system operated by a regional transmission organization.
Competitive transition charge—A nonbypassable charge applied to the bill of every customer accessing the transmission or distribution network which charge is designed to recover an electric utility’s transition or stranded costs.
Cost recovery period—The longer of:
(ii) The period during which an EDC operates under a Commission-approved generation rate plan that has been approved prior to or within 1 year of February 28, 2005, but the cost-recovery period under the act may not extend beyond December 31, 2010.
Customer-generator—A retail electric customer that is a nonutility owner or operator of a net metered distributed generation system with a nameplate capacity of not greater than 50 kilowatts if installed at a residential service or not larger than 3,000 kilowatts at other customer service locations, except for customers whose systems are above 3 megawatts and up to 5 megawatts who make their systems available to operate in parallel with the electric utility during grid emergencies as defined by the regional transmission organization or where a microgrid is in place for the primary or secondary purpose of maintaining critical infrastructure, such as homeland security assignments, emergency services facilities, hospitals, traffic signals, wastewater treatment plants or telecommunications facilities, provided that technical rules for operating generators interconnected with facilities of an EDC, electric cooperative or municipal electric system have been promulgated by the institute of electrical and electronic engineers and the Commission.
DSP—Default service provider—An EDC within its certified service territory or an alternative supplier approved by the Commission that provides generation service when one of the following conditions occurs:
(ii) A retail electric customer does not choose an alternative EGS.
Department—The Department of Environmental Protection of the Commonwealth.
EDC—Electric distribution company—The public utility providing facilities for the jurisdictional transmission and distribution of electricity to retail customers, except building or facility owners/operators that manage the internal distribution system serving the building or facility and that supply electric power and other related electric power services to occupants of the building or facility.
EGS—Electric generation supplier—
(iii) The term excludes electric cooperative corporations except as provided in 15 Pa.C.S. Chapter 74 (relating to generation choice for customers of electric cooperatives).
Force majeure—
(i) Upon its own initiative or upon a request of an EDC or an EGS, the Commission, within 60 days, will determine if alternative energy resources are reasonably available in the marketplace in sufficient quantities for the EDCs and the EGSs to meet their obligations for that reporting period under the act. In making this determination, the Commission will consider whether EDCs or EGSs have made a good faith effort to acquire sufficient alternative energy to comply with their obligations. Evidence of good faith efforts include:
(iv) If the Commission modifies the EDC or EGS obligations under the act, the Commission may require the EDC or EGS to acquire additional alternative energycredits in subsequent years equivalent to the obligation reduced by a force majeure declaration when the Commission determines that sufficient alternative energy credits exist in the marketplace.
Grid emergencies—An emergency condition as defined in the PJM Interconnection, LLC Open Access Transmission Tariff or successor document.
kW—Kilowatt—A unit of power representing 1,000 watts. A kW equals 1/1000 of a MW.
MW—Megawatt—A unit of power representing 1,000,000 watts. An MW equals 1,000 kWs.
Microgrid—A system analogous to the term distributed resources (DR) island system, when parts of the electric distribution system have DR and critical infrastructure load in a combination so as to give the EDC the ability to safely and intentionally disconnect that section of the distribution system from the rest of the distribution system and operate it as an island during emergency situations.
Moving water impoundment—A physical feature that confines, restricts, diverts or channels the flow of surface water, including in-stream hydroelectric generating technology and equipment.
Municipal solid waste—The term includes energy from existing waste to energy facilities which the Department has determined are in compliance with current environmental standards, including the applicable requirements of the Clean Air Act (42 U.S.C.A. § § 7401—7671q) and associated permit restrictions and the applicable requirements of the Solid Waste Management Act (35 P.S. § § 6018.101—6018.1003).
RTO—Regional transmission organization—An entity approved by the FERC that is created to operate and manage the electrical transmission grids of the member electric transmission utilities as required under FERC Order 2000, Docket No. RM99-2-000, FERC Chapter 31.089 (1999) or any successor organization approved by the FERC.
Reporting period—The 12-month period from June 1 through May 31. A reporting year shall be numbered according to the calendar year in which it begins and ends.
Retail electric customer—
(ii) The term excludes an occupant of a building or facility where the following apply:
(C) The occupants are not direct purchasers.
Stranded costs—An electric utility’s known and measurable net electric generation-related costs, determined on a net present value basis over the life of the asset or liability as part of its restructuring plan, which traditionally would be recoverable under a regulated environment but which may not be recoverable in a competitive electric generation market and which the Commission determines will remain following mitigation by the electric utility.
Tier I alternative energy source—Energy derived from:
(viii) Coal mine methane.
Tier II alternative energy source—Energy derived from:
(vii) Integrated combined coal gasification technology.
True-up period—The period each year from the end of the reporting year until September 1.
Useful thermal energy—
(ii) The term does not apply to the use of thermal energy used in combined-cycle electric generation facilities.
Utility—
The provisions of this § 75.1 amended 66 Pa.C.S. § § 501, 1501 and 2807(e); and sections 1648.7(a) and 1648.3(e)(2) of the Alternative Energy Portfolio Standards Act of 2004 (73 P.S. § § 1648.7(a) and 1648.3(e)(2)).
The provisions of this § 75.1 amended November 28, 2008, effective November 29, 2008, 38 Pa.B. 6473; amended November 18, 2016, effective November 19, 2016, 46 Pa.B. 7277, 7448. Immediately preceding text appears at serial pages (340985) to (340986), (340013) to (340014) and (342487) to (342488).
This section cited in 52 Pa. Code § 69.2103 (relating to definitions); and 52 Pa. Code § 75.66 (relating to force majeure).