In preparing the Annual Resource Planning Report required by this subchapter, each EDC shall use the current forms and schedules specified by the Commission, which shall include the following:
- (1) ARPR 1—Historical and Forecast Energy Demand.
- (2) ARPR 2—Historical and Forecast Connected Peak Load.
- (3) ARPR 3—Historical and Forecast Number of Connected Customers.
- (4) ARPR 4—Historical and Forecast Peak Load and Energy.
- (5) ARPR 5—Existing Generating Capability.
- (6) ARPR 6—Future Generating Capability Installations, Changes and Removals.
- (7) ARPR 7—Projected Capacity and Demand.
- (8) ARPR 8—Qualifying Facility and Independent Power Production Facilities.
- (9) ARPR 9—Scheduled Imports and Exports.
- (10) ARPR 10—Summary of Demands, Resources and Energy for the Previous Year.
- (11) ARPR 11—Transmission Line Projection.
- (12) ARPR 12—Conservation and Loan Management Program Description.
Authority
The provisions of this § 57.152 amended under the Public Utility Code, 66 Pa.C.S. § § 501, 524, 1501, 1504 and 2809.
Source
The provisions of this § 57.152 amended February 25, 2000, effective February 26, 2000, 30 Pa.B. 1129. Immediately preceding text appears at serial pages (250669) to (250670).