(a) The Annual Resource Planning Report (ARPR) shall include a forecast of energy demand in megawatt-hours per calendar year.
- (1) The data shall include actual data for the past year and estimated data for the ensuing 5 years.
(2) The data shall be displayed by the following component parts:
- (i) Residential, commercial and industrial sectors.
- (ii) Other demand, including public street and highway lighting, other sales to public authorities and sales to railroads and railways.
- (iii) Sales for resale.
- (iv) Total consumption, as the sum of (i), (ii) and (iii).
- (v) System losses and company use.
- (vi) Net energy for load, as (iv) minus (v).
(b) The ARPR shall include a forecast of connected peak load.
- (1) The data shall include actual data for the past year and estimated data for the ensuing 5 years.
(2) The data shall be displayed by the following component parts:
- (i) Peak loads for both summer and winter seasons, the latter being the winter following the summer of the past year.
- (ii) The date and time of the summer and winter peak loads.
- (iii) Annual peak load.
- (iv) Annual load factor.
- (3) The summer season is June through September and the winter season is December through March.
(c) The ARPR shall include a forecast of the number of connected customers.
- (1) The data shall include actual data for the past year and estimated data for the ensuing 5 years.
(2) The data shall be displayed by the following component parts:
- (i) Residential, commercial and industrial sectors.
- (ii) Other, including public street and highway lighting, other sales to public authorities and sales to railroads and railways.
- (iii) Total number of customers.
- (d) The ARPR shall include an aggregate forecast of energy demand and peak load for the EDC’s control area and appropriate regional reliability council, as defined under § 57.192 (relating to definitions). The data shall include actual data for the past year and estimated data for the ensuing 5 years.
Authority
The provisions of this § 57.142 amended under the Public Utility Code, 66 Pa.C.S. § § 501, 524, 1501, 1504 and 2809.
Source
The provisions of this § 57.142 amended February 25, 2000, effective February 26, 2000, 30 Pa.B. 1129. Immediately preceding text appears at serial pages (205867) to (205868).