An EDC may deploy a network for automatic meter reading capability if the following conditions are met:
- (1) The network is compatible with market requirements as a qualified advanced meter based on Committee review and recommendations as adopted by the Commission.
- (2) The application shall include proposed tariffs concerning any charges for deployment of the network.
(3) The application shall include, at a minimum:
- (i) A description of the system.
- (ii) Implementation time frame.
- (iii) Certification on compliance with applicable standards as provided in § 57.254 (relating to advanced meter standards).
- (iv) Implementation costs.
- (v) Summary of educational materials on new technologies.
- (vi) Impacts on customer electric bills.
- (vii) Impacts on existing and anticipated advanced metering equipment and generation services.