- (a) The applicant is under a duty to inform the Commission of a material change in the information provided in the application during the pendency of the application, or while the licensee is operating in this Commonwealth.
(b) A material change in the organizational structure or operation that affects an applicant’s or a licensee’s operation in this Commonwealth shall be reported to the Commission within 30 days of the date of the change. Specifically, notification shall be given to the Commission of a change in the following:
- (1) The ownership of generation or transmission facilities or other inputs to electric power production.
- (2) An affiliation with an EDC, or an entity which owns generation or transmission facilities or other inputs to electric power production.
- (3) An affiliation with an entity that has a franchised service area.
- (c) Unless directed otherwise by the Commission, the licensee does not need to file an amended application with the Commission.