(a) Plan submission.
- (1) Each EDC shall submit to the Commission for approval an updated universal service and energy conservation plan every 3 years beginning February 28, 2000, on a staggered schedule.
- (2) The plan should cover the next 3-calendar years.
- (3) The plan should state how it differs from the previously approved plan.
- (4) The plan should include revisions based on analysis of program experiences and evaluations.
- (5) If the Commission rejects the plan, the EDC shall submit a revised plan under the order rejecting or directing modification of the plan as previously filed. If the order rejecting the plan does not state a timeline, the EDC shall file its revised plan within 45 days of the entry of the order.
- (6) The Commission will act on the plans within 90 days of the EDC filing date.
(b) Plan contents. The components of universal service and energy conservation may include the following: CAP, LIURP, CARES, Hardship Funds and other programs, policies and protections. For each component of universal service and energy conservation, the plan shall include, but not be limited to, the following:
- (1) Program description.
- (2) Eligibility criteria.
- (3) Projected needs assessment.
- (4) Projected enrollment levels.
- (5) Program budget.
- (6) Plans to use community-based organizations.
- (7) Organizational structure of staff responsible for universal service programs.
- (8) Explanation of any differences between the EDC’s approved plan and the implementation of that plan. The EDC should include a plan to address those differences.
Cross References
This section cited in 52 Pa. Code § 54.77 (relating to electric distribution companies with less than 60,000 residential accounts); and 52 Pa. Code § 58.2 (relating to definitions).