(a) The operator shall reimburse the Department for the cost of the services performed under this subchapter, including interest from the date the Department demands reimbursement, if the operator does one of the following:
- (1) Submits false information.
- (2) Fails to provide the services required to complete the permit application, including submission of reclamation bond.
- (3) Fails to submit a complete surface mine activities permit application within 1 year from the date of receipt of the approved consultant report, unless the report indicates that the application is not approvable for technical reasons.
- (4) Fails to mine within 3 years after obtaining a permit.
- (5) Sells, transfers or assigns the permit to an operator who does not meet the requirements of § 86.253 (relating to operator and project qualification).