(a) In addition to the other provisions in this subchapter, a well drilled through a gas storage reservoir or a gas storage reservoir protective area shall be drilled, cased and cemented as follows:
- (1) An operator shall use drilling procedures capable of controlling anticipated gas flows and pressures when drilling from the surface to 200 feet above a gas storage reservoir or gas storage horizon.
- (2) An operator shall use drilling procedures capable of controlling anticipated gas storage reservoir pressures and flows at all times when drilling from 200 feet above a gas storage reservoir horizon to the depth at which the gas storage protective casing will be installed. Operators shall use blow-out prevention equipment with a pressure rating in excess of the allowable maximum storage pressure for the gas storage reservoir.
- (3) To protect the gas storage reservoir, an operator shall run intermediate or production casing from a point located at least 100 feet below the gas storage horizon to the surface. The operator shall cement this casing by circulating cement to a point at least 200 feet above the gas storage reservoir or gas storage horizon.
- (4) When cementing casing in a well drilled through a gas storage reservoir, the operator shall insure that no gas is present in the drilling fluids in an amount that could interfere with the integrity of the cement.
- (b) A request by an operator for approval from the Department to use an alternative method or material for the casing, plugging or equipping of a well drilled through a gas storage reservoir under section 211 of the act (58 P. S. § 601.211) shall be made in accordance with § 78.75 (relating to alternative methods).
Source
The provisions of this § 78.87 adopted March 30, 2001, effective March 31, 2001, 31 Pa.B. 1736.
Cross References
This section cited in 25 Pa. Code § 78.81 (relating to general provisions).