- (1) A person who provides off-site compensatory mitigation in order to comply with a condition imposed on a permit in accordance with ORS 196.825 (5), an authorization issued in accordance with ORS 196.800 to 196.921 or a resolution of a violation of ORS 196.800 to 196.921 may make a payment for credits to an approved mitigation bank with available credits or to the Oregon Removal-Fill Mitigation Fund.
(2) Any payments for off-site compensatory mitigation made to the Oregon Removal-Fill Mitigation Fund under subsection (1) of this section must be sufficient to cover the costs and expenses of land acquisition, project design and engineering, construction, planting, monitoring, maintenance, long-term management and protection activities, administration and other costs and expenses related to the off-site compensatory mitigation, which may vary depending on the region of this state where the off-site compensatory mitigation is conducted, and shall be calculated by the Department of State Lands as follows:
- (a) If the off-site compensatory mitigation project and project costs and expenses are identified at the time of payment to the Oregon Removal-Fill Mitigation Fund, the department shall calculate the payment based on the actual costs and expenses of the off-site compensatory mitigation.
- (b) If the off-site compensatory mitigation project and project costs and expenses are not identified at the time of payment to the Oregon Removal-Fill Mitigation Fund, the department shall calculate the payment based on the estimate of costs and expenses for off-site compensatory mitigation, as set forth in rules adopted by the department, for the region of this state where the department, to the greatest extent practicable, determines the off-site compensatory mitigation may be conducted.
(3) No later than December 1 of each year, the Director of the Department of State Lands shall submit to the Legislative Assembly and the State Land Board a detailed report that specifies:
- (a) The costs and expenses related to off-site compensatory mitigation, including variations and trends in costs and expenses over time.
- (b) Efforts undertaken by the department to reduce the costs and expenses specified in paragraph (a) of this subsection.
- (c) Efforts undertaken by the department to improve efficiencies of the department related to off-site compensatory mitigation.
- (d) The effectiveness of the July 2010 “Oregon Rapid Wetland Assessment Protocol” of the department in protecting the functions and values of wetlands through off-site compensatory mitigation.
[2003 c.738 §22; 2007 c.849 §11; 2009 c.343 §10; 2011 c.370 §3; 2013 c.257 §1; 2015 c.343 §1; 2019 c.652 §3]