When requested to review and approve plans for phased construction or deferred plan submittals under the Oregon Residential Specialty Code, the following fees in addition to the applicable plan review and permit fees apply:
(2) Deferred Submittals. The fee for processing and reviewing deferred plan submittals is an amount equal to 65 percent of the building permit fee calculated according to OAR 918-480-0020 using the value of the particular deferred portion or portions of the project. This fee is in addition to the project plan review fee based on total project value.