- (1) When waiving government performance of plan review or required inspections, a building official shall require the master builder to sign a form that specifically identifies each waiver and that states that the master builder accepts the duty of performing the review and verifications.
- (2) A master builder who accepts the duty of performing a review or verification remains responsible for that duty unless released by written and signed permission of the building official. A building official may release a master builder from a review or verification by a written and signed assumption of the review or inspection duty by the building official or written and signed assumption of the review and verification duty by another master builder.
Statutory/Other Authority
ORS 455.805 & 455.810
Statutes/Other Implemented
ORS 455.805 & 455.810
History
BCD 6-2002, f. 3-25-02, cert. ef. 4-1-02