(1) Subject to OAR 918-020-0430 and 918-020-0450, a building official may waive certain jurisdictional responsibilities to a master builder on a project by project basis for the following inspections:
- (a) Drywall;
- (b) Footings and setbacks;
- (c) Foundation walls, concrete encased electrode;
- (d) Insulation;
- (e) Masonry fireplace pre-cover;
- (f) Masonry rebar;
- (g) Gutters, downspouts and foundation drains;
- (h) Roof sheathing nailing;
- (i) Suspended ceiling;
- (j) Underfloor structural; and
- (k) Wall sheathing nailing.
- (2) A building official for a jurisdiction that has a master builder program shall conduct inspections of at least 10 percent of projects built under a master builder program.
Statutory/Other Authority
ORS 455.805 & 455.810
Statutes/Other Implemented
ORS 455.805 & 455.810
History
BCD 6-2002, f. 3-25-02, cert. ef. 4-1-02