- (1) Each electric company will receive a share of the total solar photovoltaic pilot program capacity as established by Commission order.
- (2) An electric company may not solicit or accept additional capacity reservations for a solar photovoltaic pilot program once the company reaches 100 percent of its allocated solar photovoltaic pilot capacity limit.
- (3) The Commission may consider requests to adjust each electric company’s solar photovoltaic pilot capacity limit by changing the allocation of the total solar photovoltaic pilot program capacity from those established at pilot program initiation.
Statutory/Other Authority
ORS 757.360 - 757.380
Statutes/Other Implemented
ORS 757.360 - 757.380
History
PUC 2-2010, f. & cert. ef. 6-1-10