(1) Individual solar photovoltaic systems eligible for the Solar Photovoltaic Pilot Programs must have a nameplate generating capacity less than or equal to 500 kilowatts and must be:
- (a) In compliance with the siting, design, interconnection, installation, and electric output standards and codes required by the laws of Oregon;
- (b) Installed with meters or other devices to monitor and measure the quantity of energy generated;
- (c) Permanently installed in the State of Oregon by a retail electricity consumer of the electric company;
- (d) Installed in the service territory of the electric company;
- (e) First operational and on-line after the launch of the pilot programs;
- (f) Financed without expenditures under ORS 757.612 (3)(b)(B) or tax credits under 469.160 or 469.185 through 469.225;
- (g) Certified by the residential electric consumer as constructed from new components (modules, inverter, batteries, mounting hardware, etc.); and
- (h) Compliant with Commission quality and reliability requirements for solar photovoltaic systems and system installation.
- (2) Systems uninstalled before the end of the contract term are not eligible for subsequent volumetric incentive rates, other feed-in tariffs, or pilot programs during the remainder of the original contract term. These systems cannot be reinstalled for the purposes of entering a new contract under any solar photovoltaic pilot program, volumetric incentive or other feed-in tariff program in the service territory of any electric company in the State of Oregon during the original contract term of the system, except that a system may be uninstalled and reinstalled at another location under the same contract under the conditions in OAR 860-084-0280.
Statutory/Other Authority
ORS 757.360 - 757.380
Statutes/Other Implemented
ORS 757.360 - 757.380
History
PUC 2-2018, amend filed 04/12/2018, effective 04/12/2018
PUC 7-2011, f. & cert. ef. 9-30-11
PUC 2-2010, f. & cert. ef. 6-1-10