- (1) Each public utility may assess Commission-approved integration charges on wind and solar qualifying facilities that are located within the public utility's Balancing Authority Area.
- (2) The public utility bears the burden to establish the proposed integration charge or charges reflecting the costs of integrating the type of resource that will be subject to the charges.
- (3) To the extent they are to be imposed by the public utility, any integration charges must be included in the public utility's avoided cost schedules.
Statutory/Other Authority
ORS 183, ORS 756, ORS 757 & ORS 758
Statutes/Other Implemented
ORS 756.040 & ORS 758.505-758.555
History
PUC 8-2023, adopt filed 07/25/2023, effective 07/26/2023