- (1) Each gas utility shall own and maintain or have access to all testing equipment needed to make all tests of the gas required by the Commission. The Commission may approve arrangements for the gas utility to have any part of its testing done by another utility or competent party.
- (2) All testing equipment shall be of an approved type, properly maintained, and subject to the Commission’s inspection and approval. All equipment shall be open to use of qualified representatives of the Commission at any time for testing the gas distributed by the utility.
- (3) Testing equipment shall be so located and used that the sample of gas tested shall typify the gas being distributed in the system.
Statutory/Other Authority
ORS 183, 756 & 757
Statutes/Other Implemented
ORS 756.040 & 757.250
History
PUC 9-1998, f. & cert. ef. 4-28-98