(1) A proposer may protest the notice of intent to award a contract if:
- (a) The proposer is adversely affected because the proposer would be eligible to be awarded the contract in the event that the protest was successful; and
(b) The grounds for the protest are:
- (A) All lower bids or higher ranked proposals are nonresponsive; or,
- (B) The Board has failed to conduct the evaluation of proposals in accordance with the criteria or processes described in the request for proposals.
- (2) The proposer shall submit the protest to the Board in writing, before the contract is awarded, and shall specify the grounds for the protest to be considered by the Board.
- (3) The Board shall consider and respond in writing to a protest before awarding a contract.
Statutory/Other Authority
ORS 670.310 & 672.255
Statutes/Other Implemented
ORS 672.002 - 672.325
History
BEELS 2-2024, amend filed 05/14/2024, effective 05/14/2024