- (1) A walkway conforming to OAR 741-320-0080 (Standard No. 1), shall be constructed and maintained in a tunnel, upon order of the Department, only after notice to the affected railroad and hearing (in case of dispute), and be located as close as is possible to the tunnel wall, with its surface as close as possible to the top of ties.
- (2) At each end of a tunnel the walkway shall be gradually tapered in accordance with OAR 741-320-0070 (slope) to meet the base of the ballast section or an existing walkway.
Statutory/Other Authority
ORS 184.616, 184.619, 823.011 & 824.056
Statutes/Other Implemented
ORS 824.050 & 824.056
History
RS 2-1998, f. & cert. ef. 8-20-98
RS 2-1996, f. & cert. ef. 3-14-96, Renumbered from 860-044-0332
PUC 26-1985, f. & ef. 12-19-85, Order No. 85-1196
PUC 4-1983, f. & ef. 5-3-83, Order No. 83-242
PUC 13-1981, f. & ef. 12-21-81, Order No. 81-900