- (1) The Department and successful applicant shall execute a grant/loan contract prior to the disbursal of Program Funds.
- (2) Documentation of projected costs for the Project costs shall be submitted to the Department prior to the disbursal of Program Funds.
- (3) Disbursal of Program Funds for a grant will not exceed one disbursal per month and will be on a voucher basis.
- (4) Upon request the successful applicant must provide the Department with a copy of documents, studies, reports and materials developed during the Project, including a written report on the activities or results of the Project and any other information that may be reasonably requested by the Department.
- (5) Any Program Funds disbursed but not used for an approved Project must be returned to the Department.
- (6) Amendments to project grant contracts are required to change a Project’s cost, scope, objectives or timeframe.
- (7) The Department will require that a lien be placed upon the improvements in the county in which the project is located. This lien shall be in form approved by the Department and remains in effect for a period of not less than 10 years from the disbursal of the first funds.
Statutory/Other Authority
ORS 184.616, 184.619, 367.066, 367.067 & 823.011
Statutes/Other Implemented
ORS 367.066(2) & 367.067
History
RD 4-2004, f. & cert. ef. 5-20-04