Or. Admin. R. 736-149-0830
(1) Request for progress payments. Each month the contractor shall submit to the department its written request for a progress payment based upon an estimated percentage of contract completion. At the department's discretion, this request may also include the value of material to be incorporated in the completed work that has been delivered to the premises and appropriately stored. The sum of these estimates is referred to as the "value of completed work." With these estimates as a base, the department will make a progress payment to the contractor, which shall be equal to:
ORS 279.025(3)(k)
ORS 279.025(3)(k)
PRD 2-2026, temporary adopt filed 04/23/2026, effective 04/24/2026 through 10/19/2026