The following conditions apply when installation of a traffic signal has been approved:
- (1) A traffic signal warrant shall be met within three years after construction when a traffic signal is constructed as part of a roadway improvement project.
- (2) A traffic signal warrant shall be met within one month after the traffic signal is put into operation when a traffic signal is being constructed to accommodate additional traffic from a public or private development. If it is projected that a warrant will be met at a later time, operation of the traffic signal should be correspondingly delayed.
- (3) All approaches to a traffic signal controlled intersection must be signalized, unless a traffic engineering investigation shows that signalizing a minor public or private road is not justified.
Statutory/Other Authority
ORS 184.616, 184.619, 366.205 & 810.200
Statutes/Other Implemented
ORS 810.200 & 810.210
History
TO 5-1999, f. & cert. ef. 12-17-99