- (1) For purposes of this rule “SBDP participant” means a business that meets the qualifying criteria established in OAR 731-065-0020.
(2) ODOT may select a public improvement project to be in the SBDP if it meets the following selection criteria, as determined by ODOT staff knowledgeable of the project and the SBDP:
- (a) Project can reasonably be performed by a SBDP participant serving as a prime contractor;
- (b) Selection of project supports the statutory purpose of expanding opportunities for small construction firms to compete for and perform public improvement contracts; and
- (c) Project has an estimated construction cost of greater than $250,000 but no more than $5,000,000.
- (3) ODOT may limit competition for projects in the SBDP to SBDP participants consistent with ORS 184.906.
- (4) ODOT may select no less than one public improvement project each calendar year to be in the SBDP. The aggregate estimated total of all projects in the SBDP awarded in one calendar year may not exceed $25,000,000.
- (5) ODOT may remove a project from the SBDP if it determines a project no longer meets selection criteria set forth in paragraph (2) or if no SBDP participant bids on the project.
Statutory/Other Authority
ORS 184.619
Statutes/Other Implemented
ORS 184.906
History
DOT 1-2026, adopt filed 06/11/2026, effective 06/11/2026