- (1) All Grant Agreements for technical assistance authorized by the Board shall have a clause that requires the retention of up to 10 percent of project funds until the final report, as required in the Grant Agreement, has been approved. Any unexpended project funds must be returned to the Commission.
- (2) The grantee must agree to complete the project as approved by the Board and within the timeframe specified in the Grant Agreement unless proposed modifications are submitted and approved by the Director prior to the beginning of any work proposed in the modification.
- (3) The Director may consider project modifications, including expansion of funded projects with moneys remaining from the original project allocation, if the purpose and intent of the amendment remains the same as the original project and the proposed activity is within the same geographic area.
- (4) The Director may authorize minor changes within the scope of the original project plan.
- (5) The grantee must submit a report at completion of the project in accordance with reporting requirements described in the Grant Agreement.
Statutory/Other Authority
ORS 541.984, ORS 541.988 & ORS 541.989
Statutes/Other Implemented
ORS 541.977-541.989
History
OAHP 1-2025, amend filed 01/31/2025, effective 01/31/2025
OAHP 1-2019, adopt filed 01/28/2019, effective 02/01/2019