Information required in the application shall be in the format specified by the Water Resources Commission. The application shall include, but not be limited to, the following:
- (1) A description of the project, in summary form, which identifies each project purpose and the geographical location of the project.
- (2) A map which shows the project in relation to the U.S. Public Land Survey as well as political boundaries such as cities and counties.
- (3) An identification of the reimbursable public benefits requested for funding, stating the benefit and the dollar amount of its value, and description of methods used to compute the value.
- (4) An allocation of all of the costs of the project by purpose.
- (5) A feasibility study for the construction, operation and maintenance of the project.
- (6) A financing plan which details project funding sources as well as repayment capability.
- (7) An environmental assessment report which identifies and evaluates both the positive and negative impacts of the project as related to public benefits.
- (8) Land use information as outlined in the Department’s Land Use Planning Procedures Guide.
- (9) Any other information or data required by the Commission.
Statutory/Other Authority
ORS 197, 536, 541 & 542
History
WRD 12-1990, f. & cert. ef. 8-8-90
WRD 9-1986, f. & ef. 7-22-86
WRD 5-1982, f. & ef. 6-1-82