(1) The Engineer of Record shall include an operations and maintenance plan with the submittals for building a new Dam or increasing Dam Height for:
- (a) Any Dam rated Significant or High Hazard; and
(b) Any Low Hazard Dam with:
- (A) A Gate or flashboard as part of the Spillway; or
- (B) A Valve on a Conduit that is not on the upstream side of the Dam.
- (2) The Department may review implementation of the operations and maintenance plan during Dam safety inspections.
(3) Operations and maintenance plans shall include, but are not limited to:
- (a) Directions for filling and emptying the reservoir when needed;
- (b) Frequency of inspection of the interior of Conduits, including qualifications and guidance for Persons conducting and reporting on this inspection;
- (c) Procedures for operation of all Gates and Valves;
- (d) Specified minimum frequency for cycling and lubrication of all Gates and Valves;
- (e) Standards for removal of trees and brush, and mowing other vegetation; including the frequency for the Dam owner to monitor vegetation and to take action to control brush if it obscures any face of the Dam, the Conduit, or the Spillway;
- (f) Frequency of routine Dam observations, including identification of changes in seepage and maximum permissible Dam deformations;
- (g) A Water release plan in the event of a flood forecast when reservoir is above the maximum safe operating level established by the Engineer of Record;
- (h) The measurement frequency for all monitoring instrumentation installed at the Dam; and
- (i) Review and evaluation of conditions of the Dam as necessary to keep the Dam in good repair and properly maintained, including actions identified in OAR 690-020-0250.
Statutory/Other Authority
ORS 536.027, 540.488
Statutes/Other Implemented
ORS 540.449, 540.488
History
WRD 3-2020, adopt filed 06/29/2020, effective 07/01/2020