Or. Admin. R. 632-015-0035
The permittee must give the department a minimum of 24 hours advance notice of plugging operations. For seismic shot hole plugging operations that are not a continuation of the initial drilling of the shot hole or part of the plugging procedures immediately following seismic program operations, the permittee must give the department a minimum of 24 hours advance notice of the plugging operations.
ORS 516.090 & 520.095
ORS 520.027 & 520.095
DGMI 2-2013, f. & cert. ef 3-21-13
GMI 2-1995, f. & cert. ef. 3-10-95
GMI 2-1990, f. 8-9-90, cert. ef. 8-31-90