Or. Admin. R. 437-007-0927
(1) Affected personnel must be notified of the potential failure zone of any tail tree, intermediate support tree and standing tree anchor.
NOTE: The potential failure zone is that area which could be impacted by the failure of any part of a tail tree, intermediate support tree or standing tree anchor as the result of forces or loads imposed on the tree by guylines, running lines or skylines.
(4) Personnel must be in the clear of the turn and out of the potential failure zone of a standing tree skyline or running line anchor before lines are tensioned.
NOTE: Personnel may be in the potential failure zone when minor positioning of the rigging is needed or to set chokers.
NOTE: "Before lines are tensioned" means before:
(5) Personnel working around tail and intermediate support trees must be in the clear of the turn and out of the potential failure zone before lines are tensioned.
NOTE: Personnel may be in the potential failure zone when minor positioning of the rigging is needed or to set chokers.
(7) A competent person must instruct affected personnel in the safe work practices required for work activity in any potential failure zone. This instruction must identify the:
ORS 654.025(2) & 656.726(4)
ORS 654.001 - 654.295
OSHA 5-2003, f. 6-2-03, cert. ef. 12-1-03