A residential care agency must meet all of the following requirements:
(1) Building plans.
(a) A residential care agency must submit to the Department for approval a set of plans and specifications for each building used for children in care operated by the residential care agency at each of the following times:
- (A) Prior to construction of a new building.
- (B) Prior to construction of an addition to an existing building.
- (C) Prior to the remodeling, modification, or conversion of a building.
- (D) In support of an application for initial license to operate as a residential care agency.
- (b) Plans must comply with all applicable state and local requirements for a building used as a residential facility, including the Oregon Structural Specialty Code (see OAR 837-040-0140), the Oregon Fire Code (see OAR 837-040-0010 and 837-040-0020), Oregon Health Authority requirements for buildings (see OAR chapter 333), the Oregon Plumbing Specialty Code (see OAR 918-750-0110 to OAR 918-750-0115), the rules of the State Fire Marshal for buildings (OAR chapter 837), and the local building, fire, and safety codes.
- (c) Plans must be drawn to scale, and must specify the date upon which construction, modification, or conversion will be completed, if applicable.
- (2) Sanitarian approval. The water supply, sewage, and garbage disposal systems must be approved by a sanitarian registered with the Environmental Health Registration Board (see OAR 338-010-0025 to 338-010-0038).
Statutory/Other Authority
ORS 409.050, ORS 418.005, ORS 418.327 & ORS 418.240
Statutes/Other Implemented
ORS 418.205 - 418.327
History
CWP 26-2022, renumbered from 413-215-0526, filed 11/28/2022, effective 12/01/2022
CWP 21-2020, minor correction filed 01/13/2020, effective 01/13/2020
CWP 22-2016, f. & cert. ef. 12-1-16
CWP 12-2016(Temp), f. & cert. ef. 7-1-16 thru 12-27-16
CWP 33-2008, f. & cert. ef. 10-17-08