- (1) Operation and Maintenance Plans must be prepared by all holders of permits other than a Basic ACDP. All sources subject to regular permit requirements are subject to operation and maintenance requirements.
(2) The purposes of the operation and maintenance plans are to:
- (a) Reduce the number of upsets and breakdowns in particulate control equipment;
- (b) Reduce the duration of upsets and downtimes; and
- (c) Improve the efficiency of control equipment during normal operations.
(3) The operation and maintenance plans must consider, but not be limited to, the following:
- (a) Personnel training in operation and maintenance;
- (b) Preventative maintenance procedures, schedule and records;
- (c) Logging of the occurrence and duration of all upsets, breakdowns and malfunctions which result in excessive emissions;
- (d) Routine follow-up evaluation of upsets to identify the cause of the problem and changes needed to prevent a recurrence;
- (e) Periodic source testing of pollution control units as required by the permit;
- (f) Inspection of internal wear points of pollution control equipment during scheduled shutdowns; and
(g) Inventory of key spare parts.
NOTE: This rule is included in the State of Oregon Clean Air Act Implementation Plan that EQC adopted under OAR 340-200-0040.
Statutory/Other Authority
ORS 468.020 & 468A.025
Statutes/Other Implemented
ORS 468A.025
History
DEQ 7-2015, f. & cert. ef. 4-16-15
DEQ 1-2005, f. & cert. ef. 1-4-05
DEQ 6-2001, f. 6-18-01, cert. ef. 7-1-01
DEQ 14-1999, f. & cert. ef. 10-14-99, Renumbered from 340-030-0044
DEQ 22-1996, f. & cert. 10-22-96
DEQ 10-1995, f. & cert. ef. 5-1-95
DEQ 4-1995, f. & cert. ef. 2-17-95
DEQ 4-1993, f. & cert. ef. 3-10-93
DEQ 23-1991, f. & cert. ef. 11-13-91
DEQ 22-1989, f. & cert. ef. 9-26-89
DEQ 6-1983, f. & cert. ef. 4-18-83