The requirements of 40 C.F.R. §124.3 are amended as specified by sections (1), (2), and (3) of this rule:
- (1) Each application from either an existing or new hazardous waste management facility for a permit will be reviewed for completeness by the Department within 60 days of its receipt.
- (2) If an applicant fails or refuses to correct deficiencies in the application, the permit may be denied and appropriate enforcement actions may be taken.
(3)
- (a) Upon request from a permit applicant, and following receipt of a complete Part B permit application, the Department shall prepare and mail to the applicant a project decision schedule;
(b) The schedule will specify target dates by which the Department intends to:
- (A) Prepare a draft permit;
- (B) Issue public notice;
- (C) Complete the public comment period; and
- (D) Issue a final permit.
Statutory/Other Authority
ORS 183, 459 & 468
Statutes/Other Implemented
ORS 466.140