- (1) The agent may issue a Certificate of Satisfactory Completion for a system installation if, the agent inspects and system and determines the system complies with applicable requirements in this division and OAR chapter 340, division 073 and the permit’s conditions.
- (2) If an agent determines an installation does not comply with the requirements in section (1) of this rule, the agent must notify the permittee in writing or post a Correction Notice on the site. The notice must explain the system deficiencies and corrective action required.
- (3) If an agent does not inspect a system within 7 days after notification of completion or waives the inspection under OAR 340-071-0170(2) or 340-071-0400(5)(d), a Certificate of Satisfactory Completion will be deemed to have been issued by operation of law. In such cases, a modified Certificate will be issued to the owner.
(4) A system may be backfilled (covered) after installation only after:
- (a) The agent has notified the permittee that the inspection will not be conducted;
- (b) The agent has inspected the system and issued a Certificate of Satisfactory Completion; or
- (c) A Certificate of Satisfactory Completion has been issued by operation of law under section (3) of this rule.
- (5) The permittee must ensure satisfactory completion of a system installation within 30 days after written notification or posting of a Correction Notice under section (2) of this rule unless the agent agrees to a later time.
- (6) A person may not connect to or use any system completed after January 1, 1974, unless a Certificate of Satisfactory Completion has been issued for the installation or deemed issued by operation of law under this rule.
- (7) Unless the agent requires otherwise, the system installer must backfill (cover) a system within 10 days after issuance of a Certificate of Satisfactory Completion for that system.
- (8) A Certificate of Satisfactory Completion is valid for a period of five years for connection of the system to the facility for which it was constructed. After the five-year period, an Authorization Notice, alteration permit, or construction-installation permit may be required under OAR 340-071-0160, 340-071-0205, or 340-071-0210.
- (9) A permittee may appeal the denial or revocation of a Certificate of Satisfactory Completion under ORS 183.310 through 183.550 and OAR chapter 340, division 11.
Statutory/Other Authority
ORS 454.625 & 468.020
Statutes/Other Implemented
ORS 454.655
History
DEQ 29-2025, amend filed 10/01/2025, effective 01/01/2026
DEQ 15-2017, amend filed 10/31/2017, effective 11/01/2017
DEQ 11-2004, f. 12-22-04, cert. ef. 3-1-05
DEQ 27-1994, f. 11-15-94, cert. ef. 4-1-95
DEQ 10-1981, f. & ef. 3-20-81