(1) Trading baseline must account for the following regulatory requirements applicable to the trading project at the time of trading project initiation:
- (a) NPDES permit requirements;
- (b) Rules the Oregon Department of Agriculture issued for an agricultural water quality management area under OAR chapter 603 division 095;
- (c) Rules the Oregon Board of Forestry issues under OAR chapter 629 divisions 610-680;
- (d) Requirements of a federal land management plan, or an agreement between a federal agency and the state;
- (e) Requirements established in a Clean Water Act Section 401 water quality certification;
- (f) Local ordinances;
- (g) Tribal laws, rules, or permits;
- (h) Other applicable rules affecting nonpoint source requirements;
- (i) Projects completed as part of compensatory mitigation, or projects required under a permit or approval issued under Clean Water Act section 404, or a supplemental environmental project used to settle a civil penalty imposed under OAR chapter 340 division 012 or the Clean Water Act; and
- (j) Regulatory requirements a designated management agency establishes to comply with a DEQ-issued TMDL, water quality management plan or another water pollution control plan adopted by rule or issued by order under ORS 468B.015 or 468B.110.
- (2) BMPs required to meet baseline requirements and BMPs used to generate additional water quality benefits and trade credits may be installed simultaneously.
Statutory/Other Authority
ORS 468.020, 468B.020, 468B.030, 468B.035 & 468B.555
Statutes/Other Implemented
ORS 468B.555
History
DEQ 15-2015, f. & cert. ef. 12-10-15